Production Orders
Production Orders Dashboard
Open orders
6
$39,263 budgeted
Cost in WIP
$25,593
spent on orders not yet complete
Unfavorable variance
$500
actual over standard, orders with output
No labor recorded
1
orders with output but no hours - their labor variance isn't real
Orders at risk
0 / 6
2 more to watch
Needs Attention
Workflow
3. Compute Standard Cost
Items
Open an item with an active BOM and routing, then compute from its page.
4. Release a Production Order
New Production Order
Budget lines generate automatically from the standard cost snapshot.
5. Log Costs & Review
Import from QuickBooks
Or open any order below, then its Inputs tab, to log a cost by hand.
Total cost booked
$25,593
Orders shown
6
Completed, hidden
1
Biggest customer
Anderson Fabrication Supply
37% of cost
Anderson Fabrication Supply
1 order · $9,546 cost 37%| Order | Status | Budget | Actual | Variance | % Used | Cost Status | Health |
|---|---|---|---|---|---|---|---|
| PO-1001 | In Progress | $12873.00 | $9546.35 | $3326.65 | 74% | On Track | On track |
Lakeshore Hardware Supply
1 order · $6,510 cost 25%| Order | Status | Budget | Actual | Variance | % Used | Cost Status | Health |
|---|---|---|---|---|---|---|---|
| PO-1007 | In Progress | $7737.90 | $6510.00 | $1227.90 | 84% | On Track | Watch |
Badger Equipment Rentals
1 order · $4,017 cost 16%| Order | Status | Budget | Actual | Variance | % Used | Cost Status | Health |
|---|---|---|---|---|---|---|---|
| PO-1003 | In Progress | $5665.50 | $4017.20 | $1648.30 | 71% | On Track | On track |
Great Lakes Storage Solutions
1 order · $3,717 cost 15%| Order | Status | Budget | Actual | Variance | % Used | Cost Status | Health |
|---|---|---|---|---|---|---|---|
| PO-1004 | In Progress | $6554.55 | $3717.00 | $2837.55 | 57% | On Track | On track |
Riverside Storage Co
1 order · $1,803 cost 7%| Order | Status | Budget | Actual | Variance | % Used | Cost Status | Health |
|---|---|---|---|---|---|---|---|
| PO-1006 | On Hold | $2642.97 | $1802.75 | $840.22 | 68% | On Track | Watch |
Prairie Fleet Services
1 order · $0 cost| Order | Status | Budget | Actual | Variance | % Used | Cost Status | Health |
|---|---|---|---|---|---|---|---|
| PO-1005 | Not Started | $3788.75 | $0.00 | $3788.75 | 0% | On Track | On track |